Question 4 - CTAL discussion
System test closure activities occur;
I . After system exit criteria are met.
II . After acceptance testing is over.
III . After all project activities are finished.
IV . After the execution of all test cases.
A.
I,II and IV are true
B.
II and IV are true
C.
I,II, III are true
D.
All of them are true