Question 25 - CTAL discussion
Which of the statement are true about risk based testing;
I . All risks have equal weights / concerns.
II . The level of risk is influenced by likelihood of the risk and impact of the risk.
III . All risks must be mitigated.
IV . Main developer quitting, during the coding phase of the project can be a project risk.
A.
I and II true B.I and III true C.II and IV true
B.
III and IV true
Your answer: