Question 9 - CTAL discussion
Select the correct statement regarding test planning and control
A.
Test controlling is a one-time activity that will occur at the beginning of the test effort.
B.
Test planning includes identifying test activities and resources required for the test effort.
C.
Complex relationships (many to many, one to many) cannot exist among test conditions, test cases and test procedures.
D.
Risk and Test coverage is not a metric for test planning and control.