Which of the following statements are true?
I . Early test planning and later test execution is an activity of sequential software development model
II . Change and configuration management are not needed for software testing activities.
III . Based on the project context, additional levels of testing like hardware-software integration testing, feature interaction testing can be done.
IV . System test planning and project planning could occur concurrently in V-model.
A.
I, II and III are true.
B.
II, III and IV are true.
C.
I, III and IV are true.
D.
I and III are true.
Your answer: