Question 79 - CTAL discussion
XYZ Company develops websites for individual users / companies. The testing team tests each build of the software once development releases it. Once testers complete the testing, they also work on coding the next build of the software. All testers and developers report to project manager. What type of independency is achieved above as per ISTQB syllabus?
A.
"No independent testers"
B.
Testing is done by a tester who is part of the development team
C.
"External Test specialists perform testing"
D.
"Testing is done by an organization external to the company"