Question 31 - CTAL discussion

Report
Export

A development house (DH) uses the V model for its projects. It delivers systems to the energy industry. In response to consumer demands, DH has been asked to create an online system for consumers to switch energy suppliers easily. There are already offerings in the marketplace for this service, but DH thinks it can provide a service which is easier to use. It will request more detailed information on homes and occupant lifestyles in order to accurately predict likely bills per quarter, and will update users if a cheaper tariff becomes available. For this new service, the specifications have been defined, code has been created, and system testing is about to start. Which of the following would form part of the entry criteria into unit testing (which will be followed by integration testing)?

I . 100 per cent decision coverage of all tariff calculations.

II . Signed-off program specification.

III . Signed-off technical specification.

IV . 100 per cent program specification coverage.

V . Compiled code.

A.
I, III and V
Answers
A.
I, III and V
B.
II and V
Answers
B.
II and V
C.
I, II and III
Answers
C.
I, II and III
D.
III, IV and V
Answers
D.
III, IV and V
Suggested answer: B