During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

A.
Monitor and Control Project Work
Answers
A.
Monitor and Control Project Work
B.
Perform Quality Assurance
Answers
B.
Perform Quality Assurance
C.
Close Project or Phase
Answers
C.
Close Project or Phase
D.
Control Scope
Answers
D.
Control Scope
Suggested answer: C