The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

A.
Planning.
Answers
A.
Planning.
B.
Executing,
Answers
B.
Executing,
C.
Monitoring and Controlling.
Answers
C.
Monitoring and Controlling.
D.
Closing.
Answers
D.
Closing.
Suggested answer: C