Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

A.
Project team
Answers
A.
Project team
B.
Focus group
Answers
B.
Focus group
C.
Change control board
Answers
C.
Change control board
D.
Project stakeholders
Answers
D.
Project stakeholders
Suggested answer: C