Which process involves monitoring the status of the project to update the project costs and managing changes to the cost baseline?

A.
Estimate Costs
Answers
A.
Estimate Costs
B.
Control Costs
Answers
B.
Control Costs
C.
Determine Budget
Answers
C.
Determine Budget
D.
Plan Cost Management
Answers
D.
Plan Cost Management
Suggested answer: B