The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

A.
Plan Human Resource Management.
Answers
A.
Plan Human Resource Management.
B.
Acquire Project Team.
Answers
B.
Acquire Project Team.
C.
Manage Project Team.
Answers
C.
Manage Project Team.
D.
Develop Project Team.
Answers
D.
Develop Project Team.
Suggested answer: B