The Plan Stakeholder Management process belongs to which Process Group?

A.
Executing
Answers
A.
Executing
B.
Initiating
Answers
B.
Initiating
C.
Planning
Answers
C.
Planning
D.
Monitoring and Controlling
Answers
D.
Monitoring and Controlling
Suggested answer: C