Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

A.
Facilitation techniques
Answers
A.
Facilitation techniques
B.
Expert judgment
Answers
B.
Expert judgment
C.
Analytical techniques
Answers
C.
Analytical techniques
D.
Variance analysis
Answers
D.
Variance analysis
Suggested answer: C