An input to Develop Project Charter is a/an:

A.
Business case.
Answers
A.
Business case.
B.
Activity list.
Answers
B.
Activity list.
C.
Project management plan.
Answers
C.
Project management plan.
D.
Cost forecast.
Answers
D.
Cost forecast.
Suggested answer: A