Which process determines the risks that may affect the project and documents their characteristics?

A.
Control Risks
Answers
A.
Control Risks
B.
Plan Risk Management
Answers
B.
Plan Risk Management
C.
Plan Risk Responses
Answers
C.
Plan Risk Responses
D.
Identify Risks
Answers
D.
Identify Risks
Suggested answer: D