Lessons learned are created and project resources are released in which Process Group?

A.
Planning
Answers
A.
Planning
B.
Executing
Answers
B.
Executing
C.
Closing
Answers
C.
Closing
D.
Initiating
Answers
D.
Initiating
Suggested answer: C