The Monitoring and Controlling Process Group includes processes that:

A.
Establish the scope, objectives, and course of action of a project,
Answers
A.
Establish the scope, objectives, and course of action of a project,
B.
Define a new project or a new phase of an existing project.
Answers
B.
Define a new project or a new phase of an existing project.
C.
Track, review, and regulate the progress and performance of a project.
Answers
C.
Track, review, and regulate the progress and performance of a project.
D.
Complete the work defined in the project management plan.
Answers
D.
Complete the work defined in the project management plan.
Suggested answer: C