Which grid shows which resources are tied to work packages?

A.
Work breakdown structure (WBS)
Answers
A.
Work breakdown structure (WBS)
B.
Responsibility assignment matrix (RAM)
Answers
B.
Responsibility assignment matrix (RAM)
C.
Project assignment chart
Answers
C.
Project assignment chart
D.
Personnel assignment matrix
Answers
D.
Personnel assignment matrix
Suggested answer: B