Question 124 - CAPM discussion
The process of prioritizing risks for further analysis or action is known as:
A.
Plan Risk Management.
B.
Plan Risk Responses.
C.
Perform Qualitative Risk Analysis.
D.
Perform Quantitative Risk Analysis.