The process of prioritizing risks for further analysis or action is known as:

A.
Plan Risk Management.
Answers
A.
Plan Risk Management.
B.
Plan Risk Responses.
Answers
B.
Plan Risk Responses.
C.
Perform Qualitative Risk Analysis.
Answers
C.
Perform Qualitative Risk Analysis.
D.
Perform Quantitative Risk Analysis.
Answers
D.
Perform Quantitative Risk Analysis.
Suggested answer: C