Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

A.
Historical relationships
Answers
A.
Historical relationships
B.
Dependency determination
Answers
B.
Dependency determination
C.
Bottom-up estimating
Answers
C.
Bottom-up estimating
D.
Rolling wave planning
Answers
D.
Rolling wave planning
Suggested answer: D