Specification of both the deliverables and the processes is the focus of:

A.
Change control
Answers
A.
Change control
B.
Configuration control
Answers
B.
Configuration control
C.
Project monitoring and control
Answers
C.
Project monitoring and control
D.
Issue control
Answers
D.
Issue control
Suggested answer: B