Question 169 - CAPM discussion
A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?
A.
Plan Stakeholder Management
B.
Identify Stakeholders
C.
Manage Stakeholder Engagement
D.
Control Stakeholder Engagement