The zero duration of milestones in project planning occurs because milestones:
A.
Are unpredictable and challenge the Plan Schedule Management process.
B.
Occur at random times in the project plans.
C.
Represent a moment in time such as a significant project point or event.
D.
Represent both significant and insignificant points in the project and are difficult to anticipate.