Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

A.
Procurement documents
Answers
A.
Procurement documents
B.
Inspection and audits
Answers
B.
Inspection and audits
C.
Estimate budget
Answers
C.
Estimate budget
D.
Risk register
Answers
D.
Risk register