Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:

A.
Available organizational assets
Answers
A.
Available organizational assets
B.
Project staff assignments
Answers
B.
Project staff assignments
C.
Interpersonal skills
Answers
C.
Interpersonal skills
D.
Enterprise environmental factors
Answers
D.
Enterprise environmental factors
Suggested answer: A