The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

A.
exploit
Answers
A.
exploit
B.
avoid
Answers
B.
avoid
C.
mitigate
Answers
C.
mitigate
D.
share
Answers
D.
share
Suggested answer: C