The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?

A.
-2,000
Answers
A.
-2,000
B.
-1,000
Answers
B.
-1,000
C.
1,000
Answers
C.
1,000
D.
2,000
Answers
D.
2,000
Suggested answer: B