The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?

A.
0.83
Answers
A.
0.83
B.
0.9
Answers
B.
0.9
C.
1.11
Answers
C.
1.11
D.
1.33
Answers
D.
1.33
Suggested answer: C