Which Define Activities tool or technique is used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts?

A.
Decomposition
Answers
A.
Decomposition
B.
Inspection
Answers
B.
Inspection
C.
Project analysis
Answers
C.
Project analysis
D.
Document analysis
Answers
D.
Document analysis
Suggested answer: A