Question 227 - CAPM discussion
A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?
A.
Work breakdown structure
B.
Requirements document
C.
Project charter
D.
Project management plan