A projects purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

A.
Work breakdown structure
Answers
A.
Work breakdown structure
B.
Requirements document
Answers
B.
Requirements document
C.
Project charter
Answers
C.
Project charter
D.
Project management plan
Answers
D.
Project management plan
Suggested answer: C