Which items are an output of the Perform Integrated Change Control process?

A.
Work performance reports
Answers
A.
Work performance reports
B.
Accepted deliverables
Answers
B.
Accepted deliverables
C.
Project management plan updates
Answers
C.
Project management plan updates
D.
Organizational process assets
Answers
D.
Organizational process assets
Suggested answer: C