The cost baseline and project funding requirements are outputs of which process in Project Cost Management?

A.
Estimate Costs
Answers
A.
Estimate Costs
B.
Control Costs
Answers
B.
Control Costs
C.
Plan Cost Management
Answers
C.
Plan Cost Management
D.
Determine Budget
Answers
D.
Determine Budget
Suggested answer: D