The process of defining how the project scope will be validated and controlled is known as:

A.
Define Scope.
Answers
A.
Define Scope.
B.
Develop Project Management Plan.
Answers
B.
Develop Project Management Plan.
C.
Plan Scope Management.
Answers
C.
Plan Scope Management.
D.
Plan Quality Management.
Answers
D.
Plan Quality Management.
Suggested answer: C