Question 246 - CAPM discussion

Report
Export

A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?

A.
Strong
Answers
A.
Strong
B.
Weak
Answers
B.
Weak
C.
Managed
Answers
C.
Managed
D.
Balanced
Answers
D.
Balanced
Suggested answer: D