Stakeholder communication requirements should be included as a component of:

A.
enterprise environmental factors
Answers
A.
enterprise environmental factors
B.
organizational process assets
Answers
B.
organizational process assets
C.
the project management plan
Answers
C.
the project management plan
D.
the stakeholder register
Answers
D.
the stakeholder register
Suggested answer: C