Question 278 - CAPM discussion

Report
Export

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

A.
Communication models.
Answers
A.
Communication models.
B.
Stakeholder participation.
Answers
B.
Stakeholder participation.
C.
Expert judgment
Answers
C.
Expert judgment
D.
Enterprise environmental factors.
Answers
D.
Enterprise environmental factors.
Suggested answer: C