Completion of the product scope is measured against the product:

A.
prototypes
Answers
A.
prototypes
B.
requirements
Answers
B.
requirements
C.
analyses
Answers
C.
analyses
D.
benchmarks
Answers
D.
benchmarks
Suggested answer: B