Question 286 - CAPM discussion

Report
Export

Which Control Stakeholder Engagement tool or technique allows the project manager to consolidate and facilitate distribution of reports?

A.
Information management systems
Answers
A.
Information management systems
B.
Work performance reports
Answers
B.
Work performance reports
C.
Stakeholder analysis
Answers
C.
Stakeholder analysis
D.
Data gathering and representation
Answers
D.
Data gathering and representation
Suggested answer: A