The scope management plan and scope baseline are contained in:

A.
organizational process assets
Answers
A.
organizational process assets
B.
a requirements traceability matrix
Answers
B.
a requirements traceability matrix
C.
the project charter
Answers
C.
the project charter
D.
the project management plan
Answers
D.
the project management plan
Suggested answer: D