An input to the Perform Integrated Change Control process is:

A.
expert judgment
Answers
A.
expert judgment
B.
seller proposals
Answers
B.
seller proposals
C.
the project charter
Answers
C.
the project charter
D.
the project management plan
Answers
D.
the project management plan
Suggested answer: D