Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?

A.
Define Activities
Answers
A.
Define Activities
B.
Direct and Manage Project Work
Answers
B.
Direct and Manage Project Work
C.
Develop Project Management Plan
Answers
C.
Develop Project Management Plan
D.
Develop Project Charter
Answers
D.
Develop Project Charter
Suggested answer: D

Explanation:

Topic 3, Volume C