Outputs of the Control Communications process include:

A.
expert judgment and change requests
Answers
A.
expert judgment and change requests
B.
work performance information and change requests
Answers
B.
work performance information and change requests
C.
project management plan updates and work performance information
Answers
C.
project management plan updates and work performance information
D.
issue logs and organizational process assets updates
Answers
D.
issue logs and organizational process assets updates
Suggested answer: B