A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:
A.
budget at completion (BAC)
B.
earned value management (EVM)
C.
to-complete performance index
D.
cost performance index