Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

A.
Monitoring and Controlling
Answers
A.
Monitoring and Controlling
B.
Initiating
Answers
B.
Initiating
C.
Planning
Answers
C.
Planning
D.
Executing
Answers
D.
Executing
Suggested answer: A