Which process is included in the Project Integration Management Knowledge Area?

A.
Manage Project Team
Answers
A.
Manage Project Team
B.
Collect Requirements
Answers
B.
Collect Requirements
C.
Sequence Activities
Answers
C.
Sequence Activities
D.
Direct and Manage Project Work
Answers
D.
Direct and Manage Project Work
Suggested answer: D