Question 334 - CAPM discussion

Report
Export

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

A.
Resource breakdown structure
Answers
A.
Resource breakdown structure
B.
Staffing management plan
Answers
B.
Staffing management plan
C.
Project organizational chart
Answers
C.
Project organizational chart
D.
Scope management plan
Answers
D.
Scope management plan
Suggested answer: B