An output of Control Schedule is:

A.
A project schedule network diagram
Answers
A.
A project schedule network diagram
B.
A schedule management plan
Answers
B.
A schedule management plan
C.
Schedule data
Answers
C.
Schedule data
D.
Schedule forecasts
Answers
D.
Schedule forecasts
Suggested answer: D