Which of the following is TRUE about most project life cycles?

A.
Staffing level is highest at the start.
Answers
A.
Staffing level is highest at the start.
B.
The stakeholders' influence is highest at the start.
Answers
B.
The stakeholders' influence is highest at the start.
C.
The level of uncertainty is lowest at the start.
Answers
C.
The level of uncertainty is lowest at the start.
D.
The cost of changes is highest at the start.
Answers
D.
The cost of changes is highest at the start.
Suggested answer: B