Which of the following is a tool and technique for Estimate Activity Durations?

A.
Parametric estimating
Answers
A.
Parametric estimating
B.
Monte Carlo analysis
Answers
B.
Monte Carlo analysis
C.
Alternatives analysis
Answers
C.
Alternatives analysis
D.
Bottom-up estimating
Answers
D.
Bottom-up estimating