Which of the following tools or techniques is used for Estimate Activity Durations?

A.
Critical path method
Answers
A.
Critical path method
B.
Rolling wave planning
Answers
B.
Rolling wave planning
C.
Precedence diagramming method
Answers
C.
Precedence diagramming method
D.
Parametric estimating
Answers
D.
Parametric estimating
Suggested answer: D